Expo 2020 Dubai
|
|
Expo 2020 Dubai, Dubai, United Arab Emirates Client: Dubai Expo 2020 Project Management Consultant: Turner & Townsend, UAE: Peter Day Senior Project Manager Project Role: Seconded into the Dubai Expo 2020 to provide in-house project management services. Primarily leading and coordinating a multi-disciplinary team from across the globe to deliver a number of confidential pavilions and front of house event architecture. |
Contents |
Overview
The World Expo is a global gathering of nations designed to find solutions to pressing challenges of our times. In 2020-2021, the event was scheduled to take place in Dubai from October 2020 - March 2021. Due to the COVID-19 pandemic, the opening was postponed to 1 October 2021.
Event project management
For mainstream and event construction project management, both types of projects require a clearly defined brief, robust project plan, shared success criteria and best practice project management tools and techniques. However, there are some differences in event construction project management processes compared to non-event construction project management.
The event industry differs from the open construction market primarily due to the impermanent nature of the built assets in event construction. Due to this, the responsibilities for the design, installation, maintenance and removal of all scope associated with the built asset tends to fall on the contractor (rather than the typical collection of different organisations and teams). This leads to differences in the way projects are procured, designed and delivered.
There are also subtle contractual differences. While the FIDIC suite of contracts are used in both instances, the transfer of title (and specifically the contractor’s materials and facilities) are often procured on a rental basis in event construction; title of materials and assets does not transfer to the client. This is due to the buildings and infrastructure being constructed on a temporary basis with the contractor’s scope extending into post-handover maintenance and post event removal.
There are also differences in procurement. The Middle East construction market typically favours a traditional procurement practice (full client design competitively tendered and awarded for the lowest price), which may lead to an adversarial environment. Conversely, the event industry uses more collaborative procurement methods such as design and build construction contracts and consultant framework agreements.
Dubai Expo 2020 has successfully adopted these collaborative principles which can be seen by contract sums and payment milestones being set early in the design process. Also, there are strong examples of integrated client, contractor and design teams all formally engaged to work collaboratively throughout the design and delivery process.
Final thoughts
General construction project management strategies such as formally engaging in commercial transparency and team collaboration early on in the delivery process provide projects and team members with the best chance of success across every type of construction project. However, it important to recognise that within each type of construction project there are subtle differences. It is important to be aware of them, be flexible and be adaptable to each individual project in order to succeed.
--ICPMA 09:57, 16 Feb 2021 (BST)
Related articles on Designing Buildings Wiki
Featured articles and news
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.
The changed R&D tax landscape for Architects
Specialist gives a recap on tax changes for Research and Development, via the ACA newsletter.
Structured product data as a competitive advantage
NBS explain why accessible product data that works across digital systems is key.
Welsh retrofit workforce assessment
Welsh Government report confirms Wales faces major electrical skills shortage, warns ECA.
A now architectural practice looks back at its concept project for a sustainable oceanic settlement 25 years on.
Copyright and Artificial Intelligence
Government report and back track on copyright opt out for AI training but no clear preferred alternative as yet.
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
Inspiration for a new 2026 wave of Irish construction professionals.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.